City office development Part L cost breakdown |
Ìý | element cost (or saving) | cost/m2 gfa £ | % of total cost |
Part L (2002) compliant scheme Construction cost of base scheme | 17,800,000 | 1,913.98 | Ìý |
Shell and core 9,300 m2 @ 1,640 | Ìý | Ìý | Ìý |
Category A fit out 6,375 m2 @ 400 | Ìý | Ìý | Ìý |
Ìý | Ìý | Ìý | Ìý |
Enhancements to scheme to comply with Part L 2005: Option 1 40% glazing | Ìý | Ìý | Ìý |
External walls, windows and doors | 81,400 | 8.75 | Ìý |
Extra over double glazed curtain walling; for solar-control glass; average U-value improvement from 2.2 to 2.0 1,300 m2 @ 40 | Ìý | Ìý | Ìý |
Extra over paint-backed glazed panels for improved insulation; average U-value improvement from 0.35 to 0.27 1,960 m2 @ 15 | Ìý | Ìý | Ìý |
Extra; increase airtightness to achieve 7 m3/hr/m2. No cost addition as standard is already achieved with unitised curtain wall 3,260 m2 @ nil | Ìý | Ìý | Ìý |
Heat source, space heating, air treatment and ventilation | (174,500) | (18.76) | Ìý |
Extra for; increased efficiency of condensing boilers to 89% 460kW @ 15 | Ìý | Ìý | Ìý |
Saving for; reduced boiler capacity and pipework sizes due to improved facade performance and heat recovery; reduction of 350 kW (350)kW @ 275 | Ìý | Ìý | Ìý |
Extra for: coefficient of performance for air cooled chillers increased to 3.1. No cost addition as chillers are typically specified to achieve this COP 806kW @ nil | Ìý | Ìý | Ìý |
Saving for; reduced chiller capacity and pipework sizes due to improved facade performance and heat recovery; reduction of 275 kW (275) kW @ 315 | Ìý | Ìý | Ìý |
Saving for; reduced power loads to mechanical plant, reduced sizing of sub-mains distribution Item @ (5,000) | Ìý | Ìý | Ìý |
Extra for; allowance for heat recovery installation to air handling plant; run-around coils Item @ 6,500 | Ìý | Ìý | Ìý |
Builders’ work in connection | 2,000 | 0.22 | Ìý |
Extra over costs of additional builders’ work in connection with heat recovery installation Item @ 2,000 | Ìý | Ìý | Ìý |
Preliminaries and contingencies | (18,900) | (2.03) | Ìý |
Contractor’s overheads, site establishment and site supervision Allow 17% Item @ (13,900) | Ìý | Ìý | Ìý |
Contingency sum Allow 5% Item @ (5,000) | Ìý | Ìý | Ìý |
Ìý | Ìý | Ìý | Ìý |
Construction cost – building only including costs of Part L compliance | 17,690,000 | 1,902.16 | Ìý |
Extra over costs of Part L compliance | (110,000) | (11.82) | (0.62) |
Ìý | Ìý | Ìý | Ìý |
Enhancements to scheme to comply with Part L 2005: Option 2 100% glazing, high performance glass, fixed louvres | Ìý | Ìý | Ìý |
External walls, windows and doors | 522,400 | 56.17 | Ìý |
Extra over double glazed curtain walling; high performance glass; average U-value improvement from 2.2 to 1.8 3,260 m2 @ 40 | Ìý | Ìý | Ìý |
Extra; increase air tightness to achieve 7m3/hr/m2. No cost addition as standard is already achieved with unitised curtain wall 3,260 m2 @ nil | Ìý | Ìý | Ìý |
Extra; fixed external shading 2,450 m2 @ 160 | Ìý | Ìý | Ìý |
Heat source, space heating, air treatment and ventilation | (57,800) | (6.22) | Ìý |
Extra for; increased efficiency of condensing boilers to 94% 470 kW @ 40 | Ìý | Ìý | Ìý |
Saving for; reduced boiler capacity and pipework sizes due to improved facade performance and heat recovery; reduction of 340 kW (340) kW @ 275 | Ìý | Ìý | Ìý |
Extra for: water cooled chillers in lieu of air cooled Item @ 10,000 | Ìý | Ìý | Ìý |
Saving for; reduced chiller capacity and pipework sizes due to improved facade performance and heat recovery; reduction of 340 kW (340) kW @ 315 | Ìý | Ìý | Ìý |
Extra for; distribution circuit to water cooled chiller; complete Item @ 100,000 | Ìý | Ìý | Ìý |
Saving for; reduced power loads to mechanical plant, reduced sizing of sub-mains distribution Item @ (5,000) | Ìý | Ìý | Ìý |
Extra for; allowance for heat recovery installation to air handling plant; thermal wheel Item @ 19,000 | Ìý | Ìý | Ìý |
Builders’ work in connection | 1,000 | 0.11 | Ìý |
Extra over costs of additional builders’ work in connection with heat recovery installation Item @ 1,000 | Ìý | Ìý | Ìý |
Preliminaries and contingencies | 104,400 | 11.23 | Ìý |
Contractor’s overheads, site establishment and site supervision Allow 17% Item @ 81,000 | Ìý | Ìý | Ìý |
Contingency sum Allow 5% Item @ 23,400 | Ìý | Ìý | Ìý |
Ìý | Ìý | Ìý | Ìý |
Construction cost – building only including costs of Part L compliance | 18,370,000 | 1,975.27 | Ìý |
Extra over costs of Part L compliance | 570,000 | 61.29 | 3.20 |
Ìý | Ìý | Ìý | Ìý |
Enhancements to scheme to comply with Part L 2005: Option 3 100% glazing | Ìý | Ìý | Ìý |
External walls, windows and doors | 735,000 | 79.03 | Ìý |
Extra over double glazed curtain walling; for low-e coating; average U-value improvement from 2.2 to 2.0; no additional cost as standard already achieved with curtain wall 3,260 m2 @ nil | Ìý | Ìý | Ìý |
Extra; increase air tightness to achieve 7m3/hr/m2. No cost addition as standard is already achieved with unitised curtain wall 3,260 m2 @ nil | Ìý | Ìý | Ìý |
Extra; motorised external shading 2,450 m2 @ 300 | Ìý | Ìý | Ìý |
Heat source, space heating, air treatment and ventilation | (57,800) | (6.22) | Ìý |
Scope of works and costs as breakdown for Option 2 | Ìý | Ìý | Ìý |
Electrical installations | 10,000 | 1.08 | Ìý |
Extra for; power supplies to motorised louvres 200 @ 50 | Ìý | Ìý | Ìý |
Special installations | 50,000 | 5.38 | Ìý |
Extra for; control wiring to motorised louvres 100 @ 500 | Ìý | Ìý | Ìý |
Builder’s work in connection | 4,000 | 0.43 | Ìý |
Extra over costs of additional builders’ work in connection with heat recovery installation and motorised louvres Item @ 4,000 | Ìý | Ìý | Ìý |
Preliminaries and contingencies | 158,800 | 17.08 | Ìý |
Contractor’s overheads, site establishment and site supervision Allow 17% Item @ 121,800 | Ìý | Ìý | Ìý |
Contingency sum Allow 5% Item @ 37,000 | Ìý | Ìý | Ìý |
Ìý | Ìý | Ìý | Ìý |
Construction cost – building only including costs of Part L compliance | 18,700,000 | 2,010.76 | Ìý |
Extra over costs of Part L Compliance | 900,000 | 96.78 | 5.06 |
Ìý | Ìý | Ìý | Ìý |
External walls, windows and doors | 551,300 | 59.28 | Ìý |
Extra; increase airtightness to achieve 7m3/hr/m2. No cost addition as standard is already achieved with unitised curtain wall 3,260 m2 @ nil | Ìý | Ìý | Ìý |
Extra over costs of; externally ventilated double wall facade with motorised blinds in lieu of standard unitised curtain wall; average U-value 1.60 2,450 m2 @ 225 | Ìý | Ìý | Ìý |
Heat source, space heating, air treatment and ventilation | (57,800) | (6.22) | Ìý |
Scope of works and costs as breakdown for Option 2 | Ìý | Ìý | Ìý |
Electrical installations | 10,000 | 1.08 | Ìý |
Extra for; power supplies to motorised louvres 200 @ 50 | Ìý | Ìý | Ìý |
Special installations | 50,000 | 5.38 | Ìý |
Extra for; control wiring to motorised louvres 100 @ 500 | Ìý | Ìý | Ìý |
Builders’ work in connection | 4,000 | 0.43 | Ìý |
Extra over costs of additional builders’ work in connection with heat recovery installation Item @ 4,000 | Ìý | Ìý | Ìý |
Preliminaries and contingencies | 122,500 | 13.17 | Ìý |
Contractor’s overheads, site establishment and site supervision Allow 17% Item @ 94,500 | Ìý | Ìý | Ìý |
Contingency sum Allow 5% Item @ 28,000 | Ìý | Ìý | Ìý |
Ìý | Ìý | Ìý | Ìý |
Construction cost – building only including costs of Part L compliance | 18,480,000 | 1,987.10 | Ìý |
Extra over costs of Part L compliance | 680,000 | 73.12 | 3.82 |